Court-appointed experts investigating the 18 January rail accident near Adamuz in Córdoba, Spain, have concluded that a poorly executed weld and subsidence of the ground were the most probable causes of the disaster, which claimed 46 lives and injured more than 150 people.
In a preliminary report dated 20 November, three engineers tasked with establishing the cause of the crash state that a 6.4-millimetre irregularity detected in October 2025 may have contributed to the fracture of the rail that caused the Iryo train to derail and collide with a Renfe Alvia service. The experts caution, however, that outstanding tests could still alter their conclusions.
A faulty weld and a track irregularity detected months earlier
According to the experts, the sinking of one rail may have generated overloads on the opposite rail as trains passed over it, progressively weakening the weld until it broke. They describe this as a 'seesaw effect'. The irregularity did not require trains to reduce speed, but it did call for closer monitoring and maintenance work. The experts say they have no evidence that such follow-up was carried out.
The weld under investigation joined a rail manufactured in 1989 to another from 2023, installed during upgrade works on the Madrid–Seville high-speed line in 2025. The two rails differed in properties and hardness, although this type of joint is covered by Adif's technical standards. Investigators have also found inconsistencies in the welding records and are examining whether the quality checks performed during the works were sufficient.
This incident has reignited scrutiny of Spain's high-speed rail infrastructure, which has faced broader reliability concerns in recent months. The accident also comes amid political tensions, with Spain's right-wing parties gaining ground in opinion polls, though the crash itself has not become a major partisan issue.
Ten months of investigation and tests still outstanding
The examining magistrate in Montoro, Cristina Pastor, has asked the Judicial Police in Córdoba to look for alternative laboratories after the Centre for Public Works Studies and Experimentation (CEDEX) reported that it lacked the means to carry out certain tests on the concrete sleepers.
Ten months after the accident, investigators are still awaiting the analysis of the rails, welds, ballast and sleepers recovered from the scene. These tests will be crucial to determine how the fracture originated and to establish any potential responsibility.
The tragedy has also drawn attention to the broader safety of European rail networks, where aging infrastructure and maintenance backlogs remain a challenge. While Spain's high-speed network is among the most extensive in the world, this incident underscores the importance of rigorous oversight and timely repairs.
As the investigation continues, families of the victims and survivors await answers. The preliminary report offers a plausible mechanism, but the final conclusions will depend on the pending laboratory results. For now, the experts' findings point to a failure that might have been prevented with proper follow-up on a known defect.